Brighter, Bolder JPL - 3rd Floor Renovation Timeline

Checkout the JPL 3rd Floor Renovation FAQ

The Vision Begins

LibQual Survey

2017, 2019Gathered feedback from multiple stakeholders and campus decision makers (I.e. student, faculty and staff surveys, and focus groups).

Visioning with Gensler design firm

3/19—04/20Focus groups held with students and staff proved the space needed improvements in available lighting, technology and study space.

COVID-19 Pandemic

3/20 With campus operations moving to remote for most of 2020 and 2021, contractors begin work to take advantage of the lower traffic on campus.

Bright, Bold JPL Windows project begins

8—10/20Windows design firm selection and assessment begins.

Strategic Investment Fund (SIF) Award

6/21University-awarded funding for new windows.

Communication to campus stakeholders

2021—2022Libraries Vice Provost & University Librarian held meetings about the project with multiple campus leadership groups, including those with faculty representation. He has also met on multiple occasions with the Student Government Association. Additional discussions with academic departments are ongoing.

SIF Award

6/22University-awarded funding for new furnishings.

Clearing the Way for a Brighter, Bolder JPL

Materials Review

1/21Librarians begin an in-depth review of 3rd-floor stacks.

Minor interior renovations begin

6/22Book shifting and deselection process begin.

New furnishings arrive and installed

Late Fall '22With the installation of the windows the 3rd floor is refreshed... new paint, new furnishings, new signage, refreshed study spaces.

"Heart of the Campus" meetings

Fall '22Libraries VP & University Library continues to update university stakeholders on renovation progress.